Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Caledonia plans to commission its offshore substation platform(s) around 2030, ahead of first power in the same year and ahead of full commercial operations in 2031/32. As a radial-connected 2 GW fixed-bottom offshore wind farm (Caledonia North + South phases), the offshore substation must be commissioned and energised before turbines can export power onshore to the SSEN New Deer substation in Aberdeenshire via the offshore export cable circuits. Year precision reflects phase-level scheduling on the developer's FAQ.