Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
Caledonia is targeting Final Investment Decision in 2027, ahead of the planned onshore construction start in 2028 per the developer's current FAQ. For a 2 GW fixed-bottom offshore wind farm in the Outer Moray Firth with consent applications under determination (onshore Aberdeenshire APP/2024 and APP/2025/1930; offshore Section 36 to Marine Scotland November 2024), an FID year typically 12-18 months before construction mobilisation, locating FID in 2027. Year precision reflects the gap between consent award (targeted 2025/26 per developer FAQ) and onshore construction (2028).