Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Commissioning of the Burbo Bank Extension onshore substation electrical apparatus was completed in 2017, after installation of all turbines on the associated wind farm was finished in April 2017. The onshore substation construction site had to remain operational longer than originally anticipated so that full‑load tests and parallel commissioning of the substation equipment could be carried out before the transmission assets were handed over to the OFTO.