Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Jan De Nul commenced installation of the 25 km 220 kV offshore export cable for the Burbo Bank Extension offshore wind farm in June 2016 using the cable laying vessel Willem de Vlamingh. The export cable connects the offshore substation in Liverpool Bay to the onshore grid connection at Bodelwyddan.