Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Broadshore targets offshore substation commissioning around 2030, before first power and full commercial operation in the early 2030s. As a radial-connected 900 MW floating wind farm connecting to the planned SSEN Netherton Hub onshore connection in the Peterhead area via HVAC export, the offshore substation platform must be commissioned and energised before turbines can export power onshore. Year precision reflects phase-level scheduling on the developer's website. The November 2025 Nadara acquisition statement frames overall portfolio delivery as mid-2030s, indicating possible slippage.