Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Broadshore plans to begin floating foundation installation in 2029 at the start of the late-2020s offshore construction phase published on the project website. As a 900 MW floating offshore wind farm in 80-100 m water depths north of Fraserburgh with floating substructure options (steel, concrete or hybrid) under design and mooring screening by First Marine Solutions, foundation installation (anchor and mooring deployment plus tow-out of floating foundations from a marshalling port such as Peterhead) is the first major offshore construction activity in the schedule and is scoped to the 2029 construction commencement. Year precision reflects phase-level scheduling on the developer's website. The November 2025 Nadara acquisition statement frames overall portfolio delivery as mid-2030s, indicating possible slippage.