Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
Broadshore plans to achieve first power around 2030 at the start of the early-2030s commercial operations window published on the project website. Per Broadshore's indicative project timeline (broadshorewind.co.uk/the-project/), construction commences in the late 2020s ahead of commercial operation in the early 2030s. For a 900 MW floating wind farm with EOLOS-validated metocean data and mooring design progressed through First Marine Solutions, first power (initial export of electricity to grid from the first energised turbines) typically follows offshore construction start by 12-24 months and precedes full commercial operations. Year precision reflects phase-level scheduling on the developer's website rather than a discrete date. The November 2025 Nadara acquisition press release framed overall portfolio delivery as mid-2030s, indicating schedule risk on this projection.