Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Asso.subsea was contracted by Končar on behalf of HOPS to provide transportation and installation services for four new 110 kV submarine cable systems, including the Travna–Slatina link between Brač and Hvar, replacing the old cables with three 630 mm² submarine cables over a total length of about 30 km and executing complex onshore pull‑ins, HDD sections and steep‑slope landings.