Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
As part of the renewal of the 110 kV submarine cable systems including the Brač–Hvar interconnector, Asso.subsea completed demanding shore‑end works and landfalls at the island landing sites, with onshore pull‑in operations preceded by preparation works and use of HDD pipes at two locations and custom‑designed rollers to manage steep slopes up to 40%. The company reports that its cable‑lay vessel Atalanti and onshore teams successfully executed three consecutive landing activities, indicating completion of landfall operations for the new Brač–Hvar and associated island cable links.