On 15 August 2024, Bowdun Offshore Wind Farm Limited applied to Ofgem for the Authority’s consent, under Standard Licence Condition 15(4) of its generation licence and paragraph 10 of Schedule 4 of the Electricity Act 1989, to exercise statutory rights of entry on land in Laurencekirk, Aberdeenshire. The application sought permission for short-duration intrusive ground investigations along the proposed cable route, substation and landfall locations to assess subsoil conditions and support the design of a safe and economical cabling solution, with ongoing discussions on landowner compensation noted in the submission.