Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
Social media and case study material from OEG Energy Group, dated 18 December 2025, describe a completed pre-lay grapnel run (PLGR) campaign on the nearshore cable system for TenneT Germany's BorWin6 project on behalf of Nexans. The PLGR is a debris clearance step that typically follows UXO survey and clearance work and is carried out once the route has been prepared. Combined with personnel CVs indicating UXO survey work in late 2023, this implies that the UXO survey, identification and clearance campaign for BorWin6's export cable route was complete by late 2025, somewhat later than the originally projected 31 October 2024 date.