Neutral
Informational - no clear directional impact
Low Impact
Minor progress or informational
By 6 February 2026, a major fabrication milestone for BorWin6 was reached at Jebel Ali, UAE, where Mammoet completed the transport, loadout, and mooring of the 5,461‑tonne offshore jacket foundation that will support the BorWin kappa offshore converter platform for TenneT’s 980 MW BorWin6 HVDC grid connection in the German North Sea.