Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
DELAYED +11mo (Apr 2026): Official planning (NEP 2037/2045, TenneT) still lists BorWin6 commissioning in 2027, but a 2027-01-01 COD is unrealistic because UXO survey only finished 2025-12-31 and cable installation must follow in 2026. Keeping the developer-stated 2027 commissioning year but shifting commercial_operations_full_power to late 2027 for a more realistic, year-end placeholder consistent with upstream delays. --- BorWin6 target commissioning 2027 per NEP 2037/2045 (2025) Startnetz Table 20.