On 6 July 2022, Dutch‑German grid operator TenneT awarded Nexans the contract for production and laying of the approximately 235‑kilometre cable system for the BorWin6 offshore grid connection, securing the supplier and installer for the 320 kV HVDC export cables that will transmit 980 MW from the German North Sea to the mainland.