Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
On 11 August 2020, power cable supplier NKT was awarded a turnkey contract valued at below EUR 250 million by TenneT to deliver and install a high-voltage direct current XLPE power cable system for the BorWin5 offshore grid connection in northern Germany, securing NKT as the export cable supplier for the project.