Projected start of BorWin4 coastal-sea (Küstenmeer) cable laying in 2026, with offshore (küstenfern) cable laying scheduled for 2027. Per Amprion's DolWin4/BorWin4 Projektfortschritt page (accessed March 2026): 'Die Seekabelverlegung für DolWin4 hat im Küstenmeer im Sommer 2025 begonnen. Für BorWin4 folgt dieser Schritt in 2026. Die küstenferne (offshore) Verlegung der Seekabel erfolgt 2027.' BorWin4 lags its sister project DolWin4 by roughly one year on the cable laying campaign, with both sharing Prysmian's cable supply contract awarded 15 September 2022. The original event record was confirmed with no date and cited the Prysmian contract-award article as source — that article covers EPC contract signing, not cable laying commencement. Corrected during manual audit review to projected 2026 with Amprion's own progress page as source.