Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
As part of the BorWin2 offshore grid connection, the BorWin beta power converter on the offshore platform was planned to begin test operation at the end of 2012. This test phase was intended to verify the performance of the 800 MW HVDC converter system that will transmit electricity from the Veja Mate and Global Tech I offshore wind farms to the German mainland.