Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
Offshore Marine Management GmbH, operating from Cuxport’s terminal at Cuxhaven with the multipurpose vessel Bourbon Enterprise, carried out seabed route clearance and preparation works for the BorWin2 offshore grid connection. On a series of seven trips, the vessel cleaned and prepared the seabed and installed concrete mattresses along the cable route between the Veja Mate and Global Tech I wind farms and the mainland, establishing the prepared corridor needed for subsequent export cable installation in the German North Sea.