By 29 April 2014, Siemens had installed the BorWin2 offshore platform in the North Sea northwest of Borkum, positioning and jacking up the 12,000‑ton self-righting BorWin beta converter platform onto its pre-installed substructure about 39 meters deep. The platform, built by Nordic Yards and equipped with Siemens HVDC technology, is a central offshore substation element of the 800 MW BorWin2 grid link between the connected wind farms and the onshore converter station at Diele.