On 3 May 2011, Nordic Yards commenced production of the BorWin beta offshore transformer platform for the BorWin2 grid connection at its Warnemünde shipyard, beginning fabrication with the first steel blank cut. Up to 450 workers were to be involved in building this first self-righting offshore power converter platform in Germany, which will transmit 800 MW of power from the Veja Mate and Global Tech I wind farms to shore as part of TenneT’s BorWin2 HVDC system.