Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
On 14 March 2022, a regulatory decision was taken to change the figure on soft-start requirements in the preliminary studies for the Bornholm Energy Island, modifying conditions attached to Energinet’s investigation permits for the project.