Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Energinet selected NKT to deliver the 525 kV HVDC on- and offshore power cable systems for the Danish connection between Bornholm Energy Island and Zealand, signing a contract valued at around EUR 650 million. The contract covers design, manufacturing and installation of approximately 200 km of offshore route and 16.8 km of onshore cables, securing the main cable link that will transmit offshore wind power from Bornholm Energy Island into the Danish grid.