Inter-array cable transport, installation and burial for Borkum Riffgrund 3 (combined contract with Gode Wind 3; 106 inter-array cables total).
Boskalis was awarded an inter-array cable installation contract by Ørsted for the German offshore wind farms Borkum Riffgrund 3 and Gode Wind 3. The contract scope comprised transport, installation, and burial of a combined total of 106 inter-array cables. Boskalis executed the work using its cable-laying vessel Boka Ocean (equipped for the campaign with a 4,000-ton turntable) and, during later project updates, also referenced the multipurpose offshore vessel Ndeavor supporting installation and burial activities at Borkum Riffgrund 3.