Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
Borkum Riffgrund 3, a 913 MW offshore wind farm jointly owned by Ørsted and Nuveen Infrastructure, delivered its first electricity to the German grid on 3 December 2025. The 83 Siemens Gamesa 11 MW turbines feed power via a 66 kV direct connection to TenneT’s DolWin epsilon offshore converter platform, marking first power for Ørsted’s largest German offshore project located about 72 km off the North Sea coast.