Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Inter-array cable installation at Borkum Riffgrund 2 started on 16 April 2018, when Van Oord’s cable-laying vessel Nexus began laying approximately 110 km of cables to connect the 56 MHI Vestas 8 MW turbines to the offshore substation and to link the wind farm with Borkum Riffgrund 1. The cables, manufactured by Nexans in Hanover, had been loaded at the port of Nordenham at the end of March.