Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Foundation installation at Borkum Riffgrund 1 was completed by late August 2014, after the 77 monopile foundations had been fully installed by the end of July and a final suction bucket jacket prototype foundation was installed at the site using a low-noise suction installation method.