Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
In June 2014, the cable‑laying vessel Boa Sub C began installing the 26 km 155 kV AC export cable system from the Borkum Riffgrund 1 offshore substation to the DolWin alpha converter platform, providing the grid connection for the wind farm.