Bockstigen · 3.3 MW57.04°N · 18.15°E · 5 km offshore
Project notessourced · 3 documents
Bockstigen is a small, historically important offshore wind farm located off southern Gotland, Sweden, originally commissioned in the late 1990s. The site comprises five early-generation machines and was one of the world’s first commercial offshore wind installations. Rather than pursue a full redevelopment, the owner-operator executed a pioneering partial repowering in 2018: nacelles, rotors and control systems from used Vestas V47 (660 kW) units were installed on the existing towers, increasing nameplate capacity modestly and more than doubling annual energy output while re-using foundations and electrical infrastructure. The work—completed in under a year and reported to have cost under €5m—focused on life-extension and resource-efficient reuse of components, delivering roughly 15 extra years of service and demonstrating a pragmatic alternative to full replacement. The repowering also reflected local grid and market constraints; a planned larger redevelopment was aborted after a proposed 400 kV mainland-Gotland link was cancelled, removing the export capacity needed for a bigger project. Installation faced challenging Baltic Sea conditions and required specialist marine lifting from a jack-up platform. The project is owned/operated by Momentum (Momentum Gruppen / Momentum Energy Group) and is widely cited as the world’s first commercial offshore wind repowering, making it a reference case for end-of-life options and multibrand component reuse in offshore fleets.
Original monopile foundations were retained during the 2018 partial repowering (only nacelles, blades and transformers replaced). A small service/platform between tower and monopile is reported in technical sources.
Lease & Site Conditions
3 fields
Water depth
5–6m
Distance from shore
5km
Operations & maintenance
O&M comments
Repowering works (Nov 2018) were carried out from a jack‑up/mobile crane; sources state towers, foundations and cabling were left unchanged, but do not describe an O&M port, SOV use, or permanent offshore accommodation.
Cable Specifications
4 fields
Bockstigen — export cable to Gotland-Valar
Valar, Gotland, Sweden
1 × 10 kV MVAC · 4 km
System:1 × 10 kV MVAC
Route length:4 km(4 subsea)
Burial depth:
Contemporary installation accounts indicate the electrical sea cable and an accompanying glass-fibre communication cable were laid from the ferry and anchored to the seabed rather than being deeply trenched; the...
Fibre optic:
A dedicated glass‑fibre communication cable was installed alongside the electrical sea cable to provide communications between the turbines and the shore control/grid connection; source material refers to this as a...