Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
On 15 September 2016, Nexans was selected by VBMS to supply the 66 kV inter-array and export subsea cable system for the Blyth Offshore Demonstrator wind farm under VBMS’s contract with EDF Energy Renewables. Nexans will manufacture and test the 66 kV subsea cable in one continuous length at its Hanover factory for delivery in 2017, with associated 66 kV connectors produced by Nexans Power Accessories in Belgium, making Blyth one of the first offshore wind projects to deploy 66 kV array and export cables.