Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
DELAYED +0mo (Apr 2026): Original projection assumed 4-day survey ending 2025-04-07. SSE Renewables ‘Notice to Mariners’ (Issue Date 01/04/2025, second issue) for the Cambois export cable route benthic survey states the survey mobilises 01 April 2025 and, allowing for weather delays, the expected completion date is 30 April 2025 (notice to remain in effect until 31 Aug 2025). No public confirmation of actual completion date found, so projection updated to the stated expected completion date. --- The April 2025 subtidal benthic survey campaign for the Berwick Bank export cable route was scheduled to finish on 7 April 2025 after four days of vessel operations, with a Notice to Mariners kept in force until 31 August to allow for possible weather-related delays.