Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
In June 2022, Berwick Bank Wind Farm Limited agreed an additional grid connection with the National Grid Energy Systems Operator (NGESO) for the Blyth/Cambois route, known as the Cambois connection. This agreement, which includes an additional offshore export cable and associated grid link into the National Grid Blyth substation in Northumberland, will enable the Berwick Bank project to reach its full 4.1 GW generating capacity via the offshore transmission infrastructure.