Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
DELAYED +2yr (Apr 2026): The latest official indicative timeline shows consents awarded for all development areas in 2027–2028, with construction commencing in the early 2030s. The March 2026 consultation materials also indicate consent determination by end-2028 and a grid connection date of Q4 2032, making a 2027 CfD/revenue-secured date look premature. Pushing revenue support to post-consent (first plausible CfD round after determination) i.e., 2029. --- According to a third-party project profile, Bellrock plans to secure revenue support via the UK Contracts for Difference (CfD) scheme, with CfDs expected to be obtained by 2027 ahead of construction and grid connection around 2030.