Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Bellrock plans to begin floating foundation installation in 2031, after offshore site preparation in 2030 and ahead of full commercial operations in 2037. As a 1.8 GW floating offshore wind farm in 70-120 m water depth 120 km east of Stonehaven, foundation installation (anchor/mooring deployment + tow-out of floating substructures) is the first major offshore construction activity. Year precision reflects phase-level scheduling.