Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
DELAYED +1yr (Apr 2026): No official source found that states FID will occur in 2028. The project’s current official timeline shows consenting awarded across development areas in 2027–2028, with construction in the early 2030s and grid connection indicated as Q4 2032 in March 2026 consultation materials. Given typical post-consent procurement/CfD sequencing for a 1.8 GW floating project, 2028 appears optimistic; shift FID to 2029 to align with consent determination by end-2028 and pre-construction activities ahead of a 2031 start. --- A project profile for the Bellrock floating offshore wind farm states that the project is scheduled to reach Final Investment Decision (FID) in 2028, following completion of planning and consenting activities between 2023 and 2026, with construction to follow thereafter.