In April 2025, the National Energy System Operator (NESO) imposed a change to Bellrock’s grid connection design, requiring the project to connect to the National Electricity Transmission System via SSEN Transmission’s proposed Hurlie substation west of Stonehaven, instead of the previously anticipated coordinated offshore substation solution, thereby altering the regulatory grid connection framework for the project.