Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
By late April 2022, all ten MingYang MySE 3.0-135 turbines at the 30 MW Beleolico offshore wind farm near Taranto had been installed and were operational, completing the turbine installation phase of Italy’s first offshore wind farm.