Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
By 11 February 2022, Van Oord’s MPI Offshore had been contracted to install the monopile foundations and ten MingYang turbines at the 30 MW Beleolico offshore wind farm off Taranto, using the installation vessel MPI Resolution; offshore foundation installation had started in the second half of 2021 and was completed by January 2022.