Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
After NKT completed the repair of the failed 220 kV export cable, the Beatrice offshore transmission system cable was re‑energised by the end of July 2025, fully restoring the export system’s capacity and allowing the 588 MW Beatrice offshore wind farm to return to full power output to the mainland grid.