Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Beatrice Offshore Windfarm Ltd’s construction programme for the Offshore Transmission Works (OfTW) indicates that the onshore transmission works, including cable installation and substation construction, are to be completed by June 2018 following a 14‑month period of civil engineering works between June 2016 and July 2017, defining June 2016 as the start of onshore construction for the Beatrice OFTO connection.