Negative
Setback or risk materialised
Medium Impact
Significant progress or notable issue
In April 2025, an unplanned transmission outage occurred on one of the two 220 kV high‑voltage AC subsea export cables in the Beatrice offshore transmission system, which is owned by Transmission Capital Partners. The fault reduced the export capacity of the Beatrice OFTO link by around 50%, temporarily limiting the amount of renewable electricity delivered from the Beatrice Offshore Windfarm to shore.