Following the April 2025 outage on one of the Transmission Capital Partners‑owned 220 kV subsea export cables at the Beatrice offshore transmission system, NKT executed a turnkey repair campaign. Using its adaptive rigid sea joints, cable handling system, and the vessel North Sea Giant, NKT located the fault, carried out jointing and replacement works, and completed the offshore repair in just 38 days from contract signing, restoring the integrity of the damaged export circuit.