Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Onshore construction for the BC-Wind offshore wind farm is planned to begin in 2026, with Polish contractor P&Q responsible for designing and building the onshore substation and export cable route, and Tele-Fonika Kable supplying and installing the cables to connect into the 400 kV Choczewo substation, following the project’s financial close and transition into the construction phase.