Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
Inelfe’s official Bay of Biscay works schedule lists a "Geotechnical campaign for the land section" in Spain running from late 2024 to Q1 2025. By April 2025, a CINEA/Red Eléctrica press release reports that, after several months of preparatory work for the land section and earthmoving for the new Gatika converter station, construction is advancing, implying that the land geotechnical investigations had already started in late 2024. Using this, the geotechnical survey start is confirmed in late 2024 (approximate date used).