Inelfe’s Bay of Biscay works schedule specifies a "Geotechnical campaign for the land section" in Spain running from late 2024 to Q1 2025. A CINEA/Red Eléctrica April 8, 2025 press release notes that, after several months dedicated to preparatory work for the land section and earthmoving at Gatika, civil works are underway, indicating that the land geotechnical campaign had been completed by the end of Q1 2025. This confirms completion of the geotechnical surveys for the land section in Q1 2025.