Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
By early May 2019, RTE and Red Eléctrica had completed extensive geological studies of the seabed for the Biscay Gulf interconnection, whose latest campaign revealed soil instability very close to the Capbreton Canyon in French waters, prompting reconsideration of the planned submarine route.