On 19 March 2025, Red Eléctrica, via Inelfe’s Bay of Biscay press area, reported that it was progressing with the dismantling of two 10 km overhead power lines between Gatika and Lemoiz in Biscay. This removal of existing lines is part of the Bay of Biscay interconnection works and is intended to reduce visual impact as the new underground HVDC link and converter station infrastructure are built along this corridor.