Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Statnett installed a temporary submarine power cable between Evje in Østfold and Teigen in Vestfold, replacing the Evje–Bastøy–Teigen route for contingency purposes. A Norwegian notice to mariners dated 21 December 2012 reports that installation of this unburied, unprotected cable had been completed and marks its route in the Oslofjord south of Bastøy.