Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
By July 2006, installation of all 30 turbines at the 90 MW Barrow Offshore Wind Farm had been completed as part of a construction programme running from March 2005 to July 2006, enabling the wind farm to enter operation.