Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
By 31 July 2025, Asso.subsea had been awarded the nearshore cable installation scope for three of TenneT’s 2 GW projects, including BalWin4. Working under main contractor Jan De Nul for TenneT, Asso.subsea will handle transportation and nearshore installation off the northwestern coast of Baltrum Island of a bundled package comprising two HVDC power cables, one metallic return cable, and one fibre optic cable for BalWin4, using the modified CLV Atalanti and specialised beaching and intertidal installation methods.