Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
On 10 November 2022, engineering firm G.E.O.S. announced it had been commissioned by grid operator TenneT to carry out planning works for the land cable sections of the NOR-9-3 and NOR-12-1 offshore wind power connection systems, including BalWin4 (NOR-9-3). The contract covers full technical approval planning, project coordination, preliminary subsoil investigations, and surveying for roughly 100 km of onshore cable route from the Baltrum/Dornumersiel landfall area to the grid connection point at the former Unterweser nuclear power plant site.